The Oaks

Commercial Landscaping Landscape Maintenance Hydromulching
Principal Client
Stevens Group Pty Ltd
Head Contractor
B & K Revegetation & Landscaping
Location
Hunter Valley, NSW
Duration
12 weeks

B & K Revegetation & Landscaping were engaged by Stevens Group Pty Ltd to deliver landscaping works at The Oaks residential estate associated with the existing golf course set in Pokolbin.

The scope involved supply and installation of garden beds, mass planted areas, swale works, tree planting, turf works, hydromulching of native seeds, steel and spade edging, decomposed granite and sandstone paving, concrete stairs and landings with stainless steel handrail, front entry statement including a sandstone clad blockwall, signage and dressed timber railing, core-filled engineered block wall with sandstone cladding and capping, entry fencing, and 6 month maintenance period.